IsoTool™ Used to Cut Out Long Seam Anomaly
By Jordan Dyck, Integral Pipeline Technologies
Client request |
A long seam defect was detected by an In-Line Inspection tool, and the client’s integrity program required that it be removed. |
The best solution |
Two 10” IsoTools were launched and tracked 27 miles, then parked on either side of the anomaly. |
Plan and deliver |
The downstream IsoTool was 30’ downstream of the cutout, and since the pipeline elevation was climbing, less than 5 bbls of The IsoTools held 120psi of pressure for 5 hours and 20 minutes while the cutout occurred. The IsoTools were |
Service completion |
The IsoTools were |